Overall Review

Goal

The overall review summarizes the demo run. It is not a regular operating manual for day-to-day club work. It is the project team's view of the current state: which work areas are usable, which points remain open, and what must be tracked before production approval.

Role and Access

RoleTask in this chapter
Project teamAssess the overall status and assign open points to follow-up work
AdministratorPlace system startup, roles and audit log in context
League administrationConfirm functional checkpoints from association setup, game operations and review

Subsections

SubsectionTopicResult
13.1Purpose of the overall reviewClassified as an acceptance and project-team page
13.2Status values and next stepsConsistent assessment for all checkpoints
13.3Functional acceptance pointsMaster data, roles, season, schedule and registrations assessed
13.4Game day and result reviewGame report, league decision, table and statistics assessed
13.5Communication and change casesBriefing communication and traceability assessed
13.6Open MVP pointsExport recorded as a currently open point
13.7Completion criterionClear rule for approved, approved-with-findings or not-approved

13.1Purpose of the Overall Review

The overall review bundles the chapters of the league operations handbook into an acceptance view. It does not replace specialist instructions: the relevant work contexts remain authoritative for actual operation.

The page answers three questions:

  • Is the work area functionally usable in the demo?
  • Is the effect traceable in the system?
  • Is there an open point that must still be tracked before production use or approval?

13.2Status Values and Next Steps

StatusMeaningNext step
okFunction has been reviewed traceably in the demoLeave evidence in the matching chapter
openFunction belongs to the scope but is not fully available yetTrack a concrete follow-up task or backlog point
errorBehavior blocks approval or corrupts dataPrioritize a bug task and test again
unclearFunctional decision or data basis is missingDocument the decision, then reassess the status
out of scopeDeliberately outside the current scopeDo not count it in demo-league acceptance

New workflows that change database state only receive ok once an audit test confirms logging for the signed-in action.

13.3Functional Acceptance Points

Work areaStatusAssessment
System startupokDemo admin and work areas exist.
Audit logokList, detail, filters and role-based access protection have been checked.
Master dataokClubs, teams, people, venues, images, rosters and training times are prepared.
MembershipsokClub roles, team roles and association roles are visibly separated.
Season/leagueokSeason, leagues, team registrations and league player lists are prepared.
ScheduleokEight WLD games exist with number, teams, venue and time.
Player listsokClub and association workflows for league player lists are documented.
LicensesokApplication, documents, follow-up question, decision and discarding a draft are traceable.
Referee availabilityokOwn and substitute availability entries are documented.
Referee assignmentokAssignments, open slots, briefings and My assignments are prepared.

13.4Game Day and Result Review

Work areaStatusAssessment
Game registrationokHome and away teams can prepare team sheets.
Recorder nominationokClubs can set game report recorders for their own team sheet.
Team sheetokLineup and coach can be entered per team sheet.
LockokLocked team sheets show Locked and prevent late submission or changes.
Recorder assignmentokLeague-side assignment for game day and venue is prepared.
Game report dataokResult, periods, events and add-on sheets can be entered.
Referee feedbackokConfirmation and objection for the game report are possible.
League decisionokReport can be returned for correction or completed as reviewed.
TableokConfirmed results flow into the table; unconfirmed results remain separated.
StatisticsokFair-play and player statistics use finally reviewed game reports.

13.5Communication and Change Cases

Work areaStatusAssessment
Game changeokDate, venue and status changes are traceable in the schedule.
Briefing communicationokHome club, away club and assigned people receive the matching context.
HistoryokChange and follow-up briefing remain visible in the briefing history.

Change cases are only assessed as complete when the functional state and the communication match.

13.6Open MVP Points

PointStatusNext step
CSV export for scheduleopenImplement export function and then check it functionally.
CSV export for tableopenImplement export function and then check it functionally.

In the current state there is no export button for schedule or table. Anyone reviewing the demo therefore assesses only the visible table and statistics state, not a download that does not exist yet.

13.7Completion Criterion

The demo league is considered fully reviewed when all MVP-relevant points are ok or every open point has a clear follow-up status.

ResultMeaning
approvedall MVP-relevant points are ok
approved-with-findingsusable, but with documented open points
not-approvedan error or unresolved decision blocks approval

An open point is not hidden in the handbook. It is continued as a bugfix task, feature task, backlog idea or plain text correction.